Tuesday, April 22, 2008

And the Geo installation continues...

Great Lakes was here again today, to plumb the humidifier to get its supply from the hot water heater, as well as add an outlet to power it. They also replaced that bad valve that wouldn't close for the 2nd stage of heat/cool.

The list of things to be completed is smaller (but is taking quite a long time to complete!):
- Consolidate humidistat with new digital unit
- Complete the control wiring

Just look at the dates between these posts! MARCH 27 until today?!?!? Nearly a MONTH!